The challenge
Snow World needed to install new industrial cooling plant. The existing structure had never been calculated for it - cooling systems at this scale impose a permanent load the original design didn't anticipate.
Complicating factor: the building stayed operational. Reinforcement had to go in without shutting the business down, which set the phasing and the working hours rather than the other way round.
Our approach
The existing structure was assessed against the new loading, establishing where reinforcement was required and where the existing frame was already adequate.
Steel reinforcement went in in phases, worked around opening hours and the cooling contractor's installation programme. Each phase was closed out to a stable interim state before the next began.
Where new load was introduced at concentrated points, the transfer into the existing primary structure was detailed and executed.
Outcome
The cooling plant sits on a structure calculated to carry it. The building remained operational throughout.
This project is representative of the industrial work we do: existing structures that have to carry more than they were ever designed for, in buildings that can't close.
Before and after
During
During
DeliveredRelated projects

Load-bearing wall removal, double portal installation
Demolition of a load-bearing wall and installation of a double steel portal system.

L-shaped opening with double steel portal
Construction of an L-shaped opening with a double steel portal frame.

Foundation repair and underpinning
Strengthening and underpinning of an existing foundation to increase bearing capacity and stability.